Route: Route 92 at First Creek
Bridge No.: J0923
Construction Start: February 14
Days closed: Through end of April
Contractor: Widel Inc.
Detour: Route 169, I-435 and Route C
Status: OPENED Friday, April 20
Daily traffic volume: 4400
Route: Route 69 South at Branch Williams Creek
Bridge No.: J0331
Construction Start: February 27, 2012
Days closed: 35
Contractor: Phillips Grading
Detour: Routes 92, I-35 and PP
Status: Fully opened May 25.
Daily traffic volume: 7,400
Route: Route 69 at BNSF Railroad north of Liberty
Construction Start: April 2012
Days closed: 47 per bridge
Contractor: KTU Constructors
Detour: A bypass will use existing intersection at Heartland Drive and crossover just south of Chandler Road to allow traffic on Route 69 to move around closure
Status:Opened Friday, June 15
Daily traffic volume: 11,181
Route: Route 69 at BNSF Railroad north of Liberty
Bridge No.: K0140
Construction Start: Spring 2012
Days closed: 47
Contractor: KTU Constructors
Detour: A bypass will use existing intersection at Heartland Drive and crossover just south of Chandler Road to allow traffic on Route 69 to move around closure
Status:Reduced to one lane. Traffic head-to-head in northbound lanes through July 26. Opened May 8
Daily traffic volume: 11,181 |