Hollister/U.S. 65 Interchange
Construction
Update for Week of August 8
Work scheduled:
* Rock blasted at various times each day along U.S. 65 south of
Route V/Business 65 in area of interchange construction
* Drain pipe installation and dirt grading and hauling along Route
V near College of the Ozarks
* Construction of new Business 65 overpass bridge
* Concrete poured for curb and barrier wall near Gage Drive
* Grading and utility relocation on Blue Sky Lane
* Concrete poured for curb and gutter and traffic signal installation
near Industrial Boulevard and Birch Road
Impact on Traffic:
* U.S. 65 traffic stopped about 5 minutes at a time for blasting
near roadway
* Two-way traffic on U.S. 65 shifted to temporary bypass (new
northbound lanes) east of existing lanes
* Heavy equipment near roadway and trucks entering/leaving construction
areas on Route V and Gage Drive west of U.S. 65
* Traffic stopped on Route 165 to allow dump trucks to cross road
* One-lane traffic on Blue Sky Lane
* Occasional one-lane traffic on Industrial Boulevard and Birch
Road
Most work taking place AWAY from traffic
Note: Large trucks and other vehicles
towing trailers should use Birch Road to access shopping center
because turning radius at Mall Road is tighter
Work zone speed limit on U.S. 65 Temporary Bypass: 35 mph.
Project background:
* Construction of U.S. 65/Business 65 interchange and separate
overpass bridge for Business 65 north of new interchange
* Widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet
north of Bus. 65/Route V to just south of Route 165)
* Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County
* Prime contractor: W.A. Ellis Construction of Independence
* Scheduled completion: Fall 2006
(For more information, call MoDOT in Springfield at 417-895-7600
or toll-free at 1-888-ASK-MoDOT.)