| Roadwork in the North Central District & Daily Lane Closures |
| Receive e-mail updates on projects |
| All work subject to change due to weather or priority adjustments.
When construction projects begin, "project status" will be noted as "active". |

Adair County
Construction Projects
Route 63 Adair & Macon Counties - Resurface 23 Miles.
APAC, Missouri, Inc. - Job #J2P0773
Location(s): From Route 6 in Adair County to Route M at Atlanta in Macon County.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Active
Estimated Completion: Fall 2008
More information about this project.
Route 6 Sullivan, Adair & Knox Counties - Resurface 37 Miles.
APAC, Missouri, Inc. - Job #J2P0773
Location(s): From Green City to Edina.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Begins Summer 2008 - See District 3 Knox County
Estimated Completion: Fall 2008
Maintenance Projects
Back to Top
Carroll County
Construction Projects
Route 65 - Add Turn Lanes at County Road 170.
Job #J2P2149
Location(s): Entrance to AEPI Biodisel Plant one mile south of Rte. Z.
Traffic Impact: TBD
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Route 24 - Bridge Replacement.
Job #J2P0417
Location(s): Over Lick Branch 1.5 miles east of Rte. 139
Traffic Impact: Bridge will be closed to traffic for approximately 45 days.
Detour: Rte. 41 to Rte. 65 to Rte. 65/24
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Future Project:
Route 41 Carroll & Saline Counties - Partial Replacement of the Missouri River Bridge at Miami.
Job No#J2P0755
Location(s): Missouri River Bridge at Miami on Rte. 41 Carroll/Saline Counties.
Traffic Impact: Bridge will be closed to traffic for up to 12 months during the rehabilitation. Research to provide alternate transportation during the closure is ongoing.
Project Status: Begins Fall 2009
Estimated Completion: Fall 2010
More information about this project.
Maintenance Projects
Back to Top
Chariton County
Construction Projects
Route 129 - Bridge Rehabilitation
Progressive Contractors, Inc. - Job #J2P0768
Location(s): Over Middle Fork of the Charition River, 2 miles south of Rte. 24.
Traffic Impact: Bridge will be closed to traffic for 45 days.
Project Status: Active
Estimated Completion: Summer 2008
Maintenance Projects
Route 3 - Cinder Seal - July 16 and July 17 - 6:30 a.m. to 4:30 p.m. - Traffic reduced to one lane from the junction of Rte. T & 3 to end north at Rte. 36.
Back to Top
Grundy County
Construction Projects
Maintenance Projects
Back to Top
Howard County
Construction Projects
Route 240 Howard & Saline Counties - Partial Replacement of the Missouri River Bridge at Glasgow.
Jensen Construction Co. - Job #J2P0793
Location(s): Missouri River Bridge at Glasgow.
Traffic Impact: Bridge will be closed to traffic for up to 12 months during the rehabilitation. Ferry service will be provided for alternate transportation during the closure and detour routes will be signed.
Project Status: Bridge Closure scheduled to begin late July to early August
Estimated Completion: Fall 2009
More information about this project.
Route 5 - Resurface 17 miles.
Lake Asphalt Paving & Construction - Job #J2M0025
Location(s): From Rte. 3 to Rte. 40.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Begin Summer 2008
Estimated Completion: Fall 2008
Maintenance Projects
Back to Top
Linn County
Construction Projects
Route 36 - Resurface .6 miles of the eastbound lanes. Job #J2P0820
Location(s): Linn/Macon County line.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Maintenance Projects
Route M - Culvert Replacement - July 17 - 8:00 a.m. to 3:00 p.m. - Section of Rte. M closed approximately six miles north of Brookfield at Hyde Rd. and will continue north one mile.
Route Y - Culvert Replacement - July 18 - 8:00 to 2:00 - Section of Rte. Y closed two miles east of the junction of Y and 139 at Dart Road and will end three miles northeast of the junction of Y and 139 at Birch Road.
Back to Top
Livingston County
Construction Projects
Route 65 - Rehabilitate three bridges.
Progressive Contractors, Inc. - Job #J2P0768B
Location(s): Just south of Farmersville.
Traffic Impact: Bridges reduced to one-lane traffic.
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Route 65 - Intersection Improvements.
APAC-Missouri, Inc. - Job #J2P2146
Location(s): 1 mile north of Rte. 190 at Co. Rd. 228/Kelsie Reeter Road. Intersection to new Chillicothe Correctional Center.
Traffic Impact: Reduced speed through intersection with lane closure Co. Rd. 228/Kelsie Reeter Road east of Rte. 65 will be closed to traffic.
Project Status: Active
Estimated Completion: Fall 2008
Route 190 - Intersection Improvements.
APAC-Missouri, Inc. - Job #J2S2153
Location(s): Intersection to Chillicothe High School
Traffic Impact: Flagger control at intersection.
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Maintenance Projects
Back to Top
Macon County
Construction Projects
Route 63 Macon & Randolph - Resurface 7 miles of the southbound lanes.
Chester Bross Construction, Inc. - Job #J2P0770
Location(s): From divided four-lane south Macon to Jacksonville.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Active
Estimated Completion: Fall 2008
More information about this project.
Route 63 Macon & Adair Counties - Resurface 23 Miles.
APAC, Missouri, Inc. - Job #J2P0773
Location(s): From Route 6 in Adair County to Route M at Atlanta in Macon County.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Active
Estimated Completion: Fall 2008
More information about this project.
Route 36 - Construct 22 miles of additional lanes from Shelbina to Macon.
This section is part of the entire project to four-lane Route 36 between Hannibal and Macon.
Chester Bross Construction, Inc. - Job #J2P0482
Location(s): Contractors currently working at Middle Fork of Salt River east of Macon.
Traffic Impact: None at this time
Project Status: Active
Estimated Completion: December 2009
More information about this project.
Route 36 - Resurface .6 miles of the eastbound lanes.
Job #J2P0820
Location(s): Macon/Linn County line.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Begins Summer 2008
Estimated Completion: Fall 2008
Maintenance Projects
Route 3 - Cinder Seal - July 16 and July 17 - 6:30 a.m. to 4:30 p.m. - Traffic reduced to one lane from the junction of Rte. T & 3 to end north at Rte. 36.
Back to Top
Mercer County
Construction Projects
Route E - Bridge Replacement.
Widel Inc. - Job #J2S2148
Location(s): Over Muddy Creek.
Traffic Impact: Bridge Closed
Project Status: Active
Estimated Completion: June 1, 2008
More information about this project.
Maintenance Projects
Route C - Culvert Replacement - July 21 from 1:00 to 4:00 - Section of roadway closed from the junction of C and 11 and will continue approximately four miles north.
Back to Top
Putnam County
Construction Projects
Route 136 - Bridge Replacements.
Emergy Sapp & Sons, Inc. - Job #J2P0448
Location(s): Over Chariton River just east of the Putnam/Schuyler County line.
Traffic Impact: Bridges will be closed for approximately three months.
Detour: Rte: 149 to Rte. 6 to Rte. 63
Project Status: Begins Fri., May 30
Estimated Completion: Summer 2008
Maintenance Projects
Back to Top
Randolph County
Construction Projects
Route 24 - Bridge Replacements.
Phillips Grading & Construction Inc. - Job #J2P0315
Location(s): Over East Fork of the Chariton River just east of Clifton Hill.
Traffic Impact: Two-lane traffic on temporary bypass.
Project Status: Active - Dirt work currently taking place to building temporary bypass.
Estimated Completion: Fall 2008
Route 63 Randolph & Macon Counties - Resurface 7 miles of the southbound lanes.
Chester Bross Construction Co. - Job #J2P0770
Location(s): From south of Macon to Jacksonville.
Traffic Impact: Traffic reduced to one lane in work zones.
Project Status: Active
Estimated Completion: Late June.
More information about this project.
Route 63 - Resurface 15 miles of the southbound lanes.
APAC Missouri, Inc. - Job #J2P0771
Location(s): From Route 24 to Boone County line.
Traffic Impact: Traffic reduced to one lane in work zones.
Project Status: Active
Estimated Completion: Late June.
More information about this project.
Maintenance Projects
Back to Top
Saline County
Construction Projects
Route 240 Saline & Carroll Counties - Partial Replacement of the Missouri River Bridge at Glasgow.
Jensen Construction Co. - Job #J2P0793
Location(s): Saline/Howard Counties - Missouri River Bridge at Glasgow.
Traffic Impact: Bridge will be closed to traffic for up to 12 months during the rehabilitation. A vehicle verry service will provide alternate transportation during the closure and detour routes will be signed.
Project Status: Bridge Closure beginning late July to early August
Estimated Completion: Fall 2009
More information about this project.
Maintenance Projects
Route P - Chip Seal Operation - Traffic reduced to one-lane on July 23 and July 24 from 8:00 to 3:30 each day. Just south of Route D and will continue west to end at Highway 240.
I-70 & 65 Clover-leafs - July 21 to July 28 - 7:00 a.m. to 4:00 p.m.
July 21: Traffic reduced to one lane on I-70 westbound beginning one and one-half miles east of Rte. YY and will continue west to end one-half mile west of Rte. YY.
July 22: The northbound Rte. 65 to I-70 westbound ramp will be closed. Traffic on I-70 westbound will be reduced to one lane.
July 23: The southbound Rte. 65 to I-70 eastbound ramp will be closed. Traffic on I-70 eastbound will be reduced to one lane.
July 28: Traffic on I-70 eastbound will be reduced to one lane beginning two miles west of Rte. 65 to end one mile east of Rte. 65.
Back to Top
Schuyler County
Construction Projects
Route 63 - Resurface 18 miles of the northbound and southbound lanes.
Job #J2P0778
Location(s): From the Iow line to Rte. 6 east.
Traffic Impact: Traffic reduced to one lane in work zones.
Project Status: Begins Summer 2008
Estimated Completion: Summer 2008
Maintenance Projects
Back to Top
Sullivan County
Construction Projects
Route 6 - Bridge Replacement.
Job #J2P0768D
Location(s): Over West Yellow Creek 3 miles west of Rte. 129.
Traffic Impact: Bridge reduced to one-lane traffic.
Project Status: Begins Summer 2008
Estimated Completion: Summer 2008
Route 6 Adair & Sullivan Counties - Resurface 27 Miles.
APAC, Missouri, Inc. - Job #J2P0773
Location(s): From Green City to the Knox County line.
Traffic Impact: Traffic reduced to one lane in work zone.
Project Status: Begin Summer 2008
Estimated Completion: Fall 2008
Maintenance Projects