| Adair County
Construction
MO 6 - Chip seal from MO 129 in Green City in Sullivan County to Chariton River near Novinger
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
MO 6 – May 20-24 one lane traffic 8 a.m. – 3 p.m. for bridge deck repair at Chariton River Bridge
Route V – one lane traffic 8 a.m. – 3 p.m. for bridge deck repair at Timber Creek Bridge.
MO 11 – May 20 one lane traffic 8 a.m. – 3 p.m. for drift removal at Hog Creek Bridge.
MO 11 – May 20-21 one lane traffic 8 a.m. – 3 p.m. for drift removal at Little Mussel Bridge.
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Audrain County
Maintenance
Route B – May 23 road closed 8 a.m. – 2 p.m. from Route J to Route D in Ralls County for culvert replacement
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Clark County
Construction
US 136 - Surface and shoulder work from just west of Medill at BNSF RxR overpass to US 27/61 interchange at Wayland
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
Route U – May 23 road closed 7 a.m. – 1 p.m. one mile west of Route A for culvert replacement.
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Knox County
Construction
Route 156 - Bridge replacement at Salt River
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Lewis County
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Lincoln County
Construction
US 61 at South Lincoln Drive - Interchange at South Lincoln Drive at Troy
Work Zone Info: One lane traffic during daytime work hours on US 61 at the overpass.
Project Status: 21% complete-Deck on overpass has been poured; Base rock being laid on east outer road.
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
MO 79 – Bridge replacement over Lost Creek at south city limits of Elsberry
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled; tentatively scheduled for bridge closure Aug. 22-Sept. 20.
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route Z - Streambank stabilization to protect bridge over Sulphur Creek 1.4 miles west of Route HH
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
MO 79 - Chip seal from the Pike County line to MO 47 near Winfield, 16.93 miles
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
MO 47 – Pavement and shoulder improvements from Hawk Point to Warrenton
Work Zone Info: Scheduled to begin mid-July; one lane traffic nighttime work hours Monday through Friday from 7 p.m. to 6 a.m.
Project Status: Project inactive - Tentatively scheduled to begin mid-July.
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route Y - Resurfacing from Route W to MO 79 near Foley, 7.537 miles
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin June 4.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route E - Resurfacing from Route UU in Silex to US 61, 5.227 miles
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin June 4.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route H -
Resurfacing from Route E south junction to Route 47 at Troy, 10.939 miles
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin June 4.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route H - May 30 one lane traffic 8 a.m. - 3 p.m. at Spring Creek Bridge for deck sealing operations.
Route H - May 30 one lane traffic 8 a.m. - 3 p.m. at Cuivre River Bridge for deck sealing operations.
Route E - May 30 one lane traffic 8 a.m. - 3 p.m. at Mill Creek Bridge for deck sealing operations.
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Macon County
Construction
Route C -Chip Seal from Macon Street in Bevier to the Randolph County line
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
US 36 – May 20-23 one lane traffic 8 a.m. – 5 p.m. from Route K to Linn Co. line for bridge washing in various locations
Route J – May 22 one lane traffic 8 a.m. – 3 p.m. for at Chariton River Bridge for drift removal.
MO 156 – May 22 road closed 9 a.m. – 5 p.m. two miles west of US 63 near LaPlata for crossing repairs performed by BNSF Railroad
US 36 – May 24 one lane traffic 6:30 a.m. – 5 p.m. from MO 149 to Linn Co. line for bridge washing in various locations.
US 36 - May 28-30 one lane traffic 6:30 a.m. – 5 p.m. from Route C to Linn Co. line for delineator installation.
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Marion County
Construction
MO 79 - Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton
Work Zone Info:
Work could begin as early as May and is expected to be completed by mid-September. Lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only.
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Hannibal Project Office-Resident Engineer Marty Lincoln
MO 168 – Preventative maintenance, hydrodemolition and resurface South River Bridge
Work Zone Info: Road to close at the bridge for approximately 10 days.
Project Status: Tentative scheduled to begin at the end of June or first of July
Estimated Completion: Fall 2013
Hannibal Project Office-Resident Engineer Marty Lincoln
Route Z – Preventative maintenance, hydrodemolition and resurface North Fork North River Bridge
Project Status: COMPLETED-OPEN TO TRAFFIC
Hannibal Project Office-Resident Engineer Marty Lincoln
Route Z -
Resurfacing from Route C west junction to US 36 at Monroe City
Work Zone Info: One lane traffic with pilot car controlling traffic through the work zone.
Project Status:Tentatively scheduled to begin June 7.
Estimated Completion: Fall 2013
Hannibal Project Office-Resident Engineer
Maintenance
Route C – May 20 road closed from 7 a.m. to 3 p.m. from Marion County Road 231 to 233 west of Warren for culvert replacement.
Route C – May 21 road closed from 7 a.m. to 3 p.m. from Marion County Road 276 to 229 east of Warren for culvert replacement.
Route MM – May 22 one lane traffic with the right turn lane closed near intersection of US 61 at Ayerco for signal loop repairs and concrete work.
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Monroe County
Construction
MO 154 - Preventative maintenance on Mark Twain Lake bridges over Elk Fork Salt River and South Fork Salt River. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail
Work Zone Info: Project inactive -
Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial Day and Labor day due to tourism and recreational use of the lake.
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
MO 15 -Shoulder work from just south of US 36 interchange to MO 154 north junction in Paris
Work Zone Info:One lane traffic with pilot car controlling traffic through the worksone
Project Status:15% complete - Performing partial depth pavement repairs 2 miles north of US 24 junction and at Crooked Creek.
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Montgomery County
Construction
MO 161 - Resurfacing from Route M to MO 19 north junction in Montgomery City, 17.75 miles
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin June 4.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route E – May 20-23 road closed 7:30 a.m. – 5 p.m. from Route DD to Route CC for culvert replacement.
Route F – May 22-24 road closed 7:30 a.m. – 5 p.m. from Fairview Road to Route JJ for culvert replacement.
MO 161 - May 29 one lane traffic 8 a.m. to noon from Route V to Route CC for deck sealing operations on the Elkhorn Bridge.
MO 161 - May 29 one lane traffic noon to 3 p.m. from Middletown to Route T for deck sealing operations on the Cuivre River Bridge.
Various Routes –May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek
Work Zone Info: Project inactive
Project Status: Project inactive - tentatively scheduled for bridge closure June 24-August 16.
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
US 61 -
Resurfacing and shoulders from south of MO 19 near New London to south of Route UU near Bowling Green, 11.85 miles
Work Zone Info: One lane traffic-55 mph work zone from 7 a.m. to 5 p.m. Mon.-Thurs.
Project Status: 75% complete - Performing rumble strip and striping operation in the north and southbound lanes.
Estimated Completion: Summer 2013
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Ralls County
Construction
US 61 - Resurfacing and shoulders from south of MO 19 near New London to south of Route UU near Bowling Green, 11.85 miles
Work Zone Info: One lane traffic-55 mph work zone from 7 a.m. to 5 p.m. Mon.-Thurs.
Project Status: 75% complete - Performing rumble strip and striping operation in the north and southbound lanes.
Estimated Completion: Summer 2013
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 79 - Pavement and shoulder improvements from Fulton Avenue at Hannibal in Marion County to Route E and N junction near Saverton
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Hannibal Project Office-Resident Engineer Marty Lincoln
Route J - Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail
Work Zone Info: Project inactive - Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake.
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Route Z - Resurfacing from Route C west junction to US 36 at Monroe City
Work Zone Info: One lane traffic with pilot car controlling traffic through the work zone.
Project Status:Tentatively scheduled to begin June 7.
Estimated Completion: Fall 2013
Hannibal Project Office-Resident Engineer
Maintenance
Route DD – May 23 road closed from 7 a.m. to 3 p.m. from Sweet Bay Lane near Central Stone to the end of pavement at Sheil and Huntington Lane and Sydney Road intersection for culvert replacement.
Various Routes –May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Randolph County
Construction
MO 3 - Shoulder work from US 24 south junction to MO 129 in Roanoke, 9 miles
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Schuyler County
Construction
US 136 - Add shoulders and ADA improvements from US 63 in Lancaster to the Scotland County line
Work Zone Info: Project inactive
Project Status: Project inactive - Pre construction meeting to be scheduled
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
Various Routes –
May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Scotland County
Maintenance
Route H – May 20 road closed 7 a.m. – 1 p.m. 3.7 miles east of MO 15 for culvert replacement.
Route D – May 21 road closed 7 a.m. – 1 p.m. .2 mile west of MO 15 for culvert replacement.
Route MM – May 22 road closed 7 a.m. – 1 p.m. 2.5 miles south of US 136 for culvert replacement.
Various Routes –May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Shelby County
See Route 36 Four-Lane Webpage
Construction
MO 15 -Shoulder work from just south of US 36 interchange to MO 154 north junction in Paris
Work Zone Info:One lane traffic with pilot car controlling traffic through the worksone
Project Status: 15% complete - Performing partial depth pavement repairs 2 miles north of US 24 junction and at Crooked Creek.
Estimated Completion: Fall 2013
Macon Project Office-Resident Engineer
Maintenance
MO 15 – May 20 one lane traffic 8 a.m. – 1 p.m. one mile south of Shelbyville at Black Creek Bridge for deck repairs in the NB lane.
Various Routes –May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Warren County
Construction
NOR I-70 - Resurface from MO 47 in Warrenton to St. Charles County line
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin week of June 3 or 10.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
SOR I-70 - Resurface from just east of MO 47 in Warrenton to St. Charles County line
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin week of May 28 or June 3.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
MO 47 – Pavement, shoulder and ADA improvements from just south of Route M/MM at Warrenton to Washington
Work Zone Info:Work begins at Marthasville May 20 one lane traffic daytime work hours; Dutzow to Missouri River Bridge at Washington-nighttime work hours Monday through Friday from 7 p.m. to 6 a.m.;
Work within the city limits of Warrenton limited work hours from 9 p.m. to 5:30 a.m.
Project Status: Project inactive - Tentatively scheduled to begin May 20.
Estimated Completion: Fall 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route F -
Resurfacing from I-70 north outer road to the end of State Maintenance at Innsbrook
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin week of May 20 or 28.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Route M -
Resurfacing from MO 47 in Warrenton to Route T
Work Zone Info: Project inactive
Project Status: 0% complete - Work tentatively scheduled to begin week of May 13 or 20.
Estimated Completion: Summer 2013
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Various Routes –May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
|