Our mission is to provide a world-class transportation experience that delights our customers and promotes a prosperous Missouri.

Road Conditions in the Northeast District

Traveler information map for northeast Missouri

If you have questions about MoDOT's work schedule, please call customer service toll-free at 1-888-275-6636 during normal business hours, or email us directly customerservice3@modot.org.

eupdate Subscribe to MoDOT's
free e-update service
to receive information
about this project
through email.

Flood Information for Northeast area:

The following roads are CLOSED due to flooding on the Mississippi River.

(Info on Salt River flooding issues - Water receding very slowly, crews anticipate the possibility of some roads opening over the weekend.

State Route 79 - PIKE COUNTY - OPEN TO TRAFFIC AT 3 P.M., THURSDAY, AUGUST 7

Salt River

Flooding between Route B and Route TT

State Route A - RALLS COUNTY - CLOSED 

Salt River
Flooding reported east and west of Route H, west of New London

Road closed since 28-JUL-08

State Route O - RALLS COUNTY - CLOSED

Salt River

Flooding from Route 61, 1.5 miles east to Flint Hill Road

Road closed since 29-JUL-08

State Route V - RALLS COUNTY - CLOSED

Salt River

Flooding reported 1.4 miles east of Bus. Route 61 at New London

Road closed since 29-JUL-08

 

All work subject to change due to weather or priority adjustments.

sign

Play the Safety Cone Game

mapCounties:

 

 

 

Audrain County
Construction Projects

Route 54 - Pace Construction Job# J3P0664, J3P0727, J3P0733 - Intersection improvements at 19 north junction at Basinger corner, and rehabilitate 13 miles of pavement

Location:  from the Route 19 north junction east 8 miles to just west of Route P and from Route 154 east 5 miles to Route U near Curryville

Work Zone Info:  Turn lane closed at 19/54; Route 54 traffic will make a turn at J and 54 to go east on Route 54.

Project Status:  17% complete - Effective Aug. 11 turn lane will be closed at Route 19/54 for approximatelyt 30 days to grade and pave for new turn lane.  There is a 10 ft. width restriction through the area at Basinger Corner and paving operations will be in progress from Basinger Corner to Vandalia.

Estimated Completion:  Fall 2008

Route 22 - Chester Bross Construction Job# J3P0726 - Rehabilitate bridge, pavement repair

Location:  From west of Route E to west of Route 15 near Mexico

Work Zone Info:  Project inactive - Traffic will be reduced to one lane at the work zone.

Project Status:  0% complete - Project inactive

Estimated Completion:  August 2009

 

Maintenance

-- Route D, DD & HH - Patching and mowing

Back to Top


Clark County
Construction Projects

Route 61 - Chester Bross Construction Job# J3P0423B - Work involves grading, paving and bridges for four-lane expressway Avenue of the Saints, minimal to no impact to traffic.

Location:  South of Wayland to Lewis County line approximately 9 miles

Work Zone Info: Traffic reduced to one lane at various locations through the 9 mile area including locations near Co. Rd. 308, Co. Rd. 378

Project Status:  92% complete - Open to traffic July 25.  Crews repairing damage to slopes, installing permanent stripes and cleanup.

Estimated Completion:  Summer 2008

See Avenue of the Saints Project Webpage

Route AA - Harry H. Houf & Sons Contractors Job # J3S0653 - Bridge replacement over Linn Creek

Location: South of Route NN near Luray

Work Zone Info: Roadway will be closed at the bridge, please use alternate routes

Project Status: 99% complete - Bridge opened to traffic 07/03/08.

Semi-final inspection was 07/07/08.  Partial acceptance for maintenance was 07/07/08.  Final acceptance is pending completion of exceptions. 

Estimated Completion:  Fall 2008

Maintenance

-- Route H - Patching

-- Various Routes - Mowing

 

Knox County
Construction Projects

Route 6 - Chester Bross Construction Job# J3P0783/J2M0023 - Resurfacing

Location:  Sullivan, Adair and Knox Counties

Work Zone Info:  Traffic will be reduced to one lane at the work zone.

Project Status:  0% complete - See District 2 Adair County

Estimated Completion:  Fall 2008

Maintenance

-- Various Routes - Patching in Scotland area and assisting with hotmix patching

Back to Top


Lewis County

Construction Projects

Route 61 - Chester Bross Construction Job# J3P0711 - Rehabilitate pavement 10 miles southbound lanes, approximately 12.86 miles

Location:  From south of Clark County line south to just south of Route C

Work Zone Info:  Traffic will be reduced to one lane at the work zone.

Project Status:  100% complete - Semi-final inspection was done 06/16/08.  Exceptions were completed. Final acceptance 07/17/08.

Estimated Completion:  Fall 2008

Maintenance

-- Various Routes - Patching, signing and mowing.

Back to Top

Lincoln County

Construction Projects

Route 79 - G & M Asphalt Co. Job# J3P0789 - Rehabilitate pavement from Pike County line to Route 47 at Winfield, 17 miles

Location:  From the Pike/Lincoln County line 3 miles south of Annada south to Route 47 near Winfield

Work Zone Info:  Traffic will be reduced to one lane at the work zone.

Project Status:  99% complete - Work completed, semi-final inspections to begin soon

Estimated Completion:  Fall 2008

Route C - APAC-Missouri, Inc. Job# J3S0765 - Rehabilitate bridges at Cuivre River and overflow

Location: East of Moscow Mills

Work Zone Info:  Traffic will be reduced to one lane at the work zone with traffic signals operating 24/7.  Short duration closures will be scheduled at a later date.

Project Status:  75% complete - Waiting on completion of corrections from semi-final inspection

Estimated Completion: Fall 2008

Route 47 - N. B. West Contracting Co. Job# J3P0747/J3P0780 - Widen Route 47, install traffic signals at H/J intersection

Location: Route 47, and Routes H and J on Route 47 at Troy

Work Zone Info: Traffic will be handled on the existing pavement during construction, but lane widths will be narrowed.

Project Status:  31% complete - Paving, installation of drainage structure and widening, misc. signal work.

Estimated Completion: Nov. 1, 2008

Maintenance
-- Route 79 - Winfield to Foley working on shoulders

Back to Top

Marion County
Construction Projects

Route 36 - Progressive Contractors Job# J3P0411B & 412B - Grading and paving for new dual divided facility, minimal to no impact to traffic.

Location:  From 0.4 mile west of Route Z to 0.2 miles east of Marion County and 0.2 mile east of Marion/Ralls Co. Line to Route 24

Work Zone Info:  Work off of traveled roadway, two-way traffic 60 mph, no restrictions or lane closures.
Project Status:  90% complete - Eastbound dirt work, stripe removal and striping; opened new railroad overpass bridge east of Monroe City west to Route Z on Thursday, Aug. 7.

Rocket to Route U, dirt work, installing permanent signs, and striping, and pouring bridge curb and approach slabs, weather permitting. Expected to open to traffic August 12.

Estimated Completion:  Fall 2008

See Route 36 Four-Lane Webpage

Route 36 - Chester Bross Construction Job# J3P0790 - Rehabilitate pavement in eastbound lanes

Location:  From Shinn Lane to Central Avenue, and westbound lanes from Central Avenue to Munger Lane in Hannibal

Work Zone Info:  Project inactive - Traffic will be reduced to one lane at the work zone.

Project Status:  0% complete - A preconstruction conference will be held at 10 a.m. Tuesday, August 12 at the Hannibal Project Office.

Estimated Completion:  Fall 2008

Maintenance

-- Various Routes - Mowing and patching

Back to Top

Monroe County

Construction Projects

Maintenance

-- Routes 154, 107 - Patching, mowing

Back to Top

Montgomery County

Construction Projects

Route 19 - Anderson Excavating and Grading Co. Job# J3P0584C - Demolition of the old Missouri River Bridge

Location:  Hermann

Work Zone Info:  Inactive-Due to high water contractor has not been able to work

Bridge Demolition-Project Status:  81% complete - Crews should finish removal of Pier 1, clam out of river and haul off.

Estimated Completion:  Summer 2008

SEE BRIDGE DEMOLITION WEBSITE

See Senator Christopher S. Bond Bridge Project Webpage

Route N - Bleigh Construction Co. Job# J3S0490 - Rehabilitate bridge over Slough and Branch Loutre River

Location:  3 miles east of Interstate 70

Work Zone Info:  Project inactive - Road will be closed at the bridge

Project Status:  0% complete - Conditions permitting, contractor will start work on project the week of August 18.

Estimated Completion:  Fall 2008

Maintenance

I-70 -- Aug. 5-16 from 7 p.m to 7 a.m. nightly eastbound driving lane closed at the 181 m.m. to repair a damaged railroad overpass.

I-70 -- Aug. 13 from 7 a.m. to 5 p.m. at the 168 mile marker, bridge work in the westbound passing lane of the Loutre River Bridge, 10 ft. width restriction through the work zone, the westbound Mineola Rest Area at the 165 mile marker will be closed during this time.

-- Various Routes - Culvert replacements

Back to Top

Pike County
Construction Projects

Route 61 - Mid-Rivers Asphalt, Inc. Job# J3P0742 - Roadway improvement on northbound lanes 0.2 mile north of Route NN known as Radar Curve

Location:  just south of Bowling Green

Work Zone Info:  Traffic will be reduced to one lane at the work zone.

Project Status:  0% complete - Staking and signing will tentatively begin 08/14/08 and dirt work will tentatively begin 08/18/08, weather permitting.

Estimated Completion:  Fall 2008

Route 79 - Boone Construction Job# J3P2157 - Slide repair south of Route TT near Ashburn

Location:  3/4 mile south of Route TT

Work Zone Info:  Road closed 3.38 miles after Route T south to 2.19 miles before Route B east.  Traffic detoured over Routes B, 61, V and T. See Pictures on Website

Project Status:  90% complete - Installing guardrail

Estimated Completion:  July 2, 2008

Maintenance

-- Route 79 - Shoulder work Ashburn area

Back to Top

Ralls County

Construction Projects

Maintenance

-- Various Routes - Mowing and patching

Back to Top

Scotland County
Construction Projects

Maintenance

-- Routes E, V, H - Patching

-- Routes EE, DD, C - Mowing

-- Various Routes - Sign work and patching

Back to Top

Shelby County
Construction Projects

Route 36 - Progressive Contractors Job# J3P0409C & 410 - Grading and paving for new dual divided facility, minimal to no impact to traffic.

Location:  From 0.6 mile west of Route 15 at Shelbina east to 0.4 mile west of Ralls County at Monroe City

Work Zone Info:  Work off of traveled roadway, two-way traffic 60 mph, no restrictions or lane closures.

Project Status:  Project Overal 20% complete - Weather permitting, all operations are active, except for grading operation will not be active this week.  Crews will be installing rock lining in various locations and erosion control active near Hunnewell and at the east end of the job.

Box Culvert at Shelbina 95% complete - Crew  finished the pour on the top slab and will start work on backfill as soon as concrete has cured.  Effective July 14 approximately 1 mile east of junction  36 & 15 there will be Stop Lights directing traffic on to a temporary by-pass.  The East & West bound lanes will be closed  and traffic will have a temporary by-pass with 11 ft. restriction at the box at this location.

North Fork Salt River Bridge - 90% complete - Crew working on bridge approach on west side.

Estimated Completion:  November 2009 completion

See Route 36 Four-Lane Webpage

Route 36 - Bross Construction Job #J2P0482 - Grading, paving and concrete girder bridges for new dual divided facility.

Location:  From east of Route 63 near Macon to west of Route 15 near Shelbina

Work Zone Info:  Work off of traveled roadway, two-way traffic 60 mph, no restriction or lane closures at this time.

Project Status:  7% complete - Macon and Shelby Counties - Contractor is continuing to install drainage structures at various locations throughout the project. They have started construction of the substructure of two bridges, Route 36 over the Middle Fork of Salt River as well as Route 36 over Route FF near South Shelby High School. Contractor has begun earthwork operations.

Estimated Completion:  Fall 2009

See Route 36 Four-Lane Webpage

Route 15 - Bleigh Const. Co. Job # J3P0510 - Bridge replacement over Messner Creek

Location: 0.7 mile south of Route M, near Bethel

Project Status: Completed - Opened to traffic August 8

Maintenance

-- Route 15 - August 12 & 13, lay asphalt between Business Route 36 and Spruce Street in Shelbina.

Back to Top

Warren County

Construction Projects

Route 47 - Pace Construction Job# J3P0708 - Rehabilitate pavement, approximately 7.68 miles

Location:  from Lincoln County line south to 0.2 mile north of Interstate 70 - from 3 miles south of Hawk Point to I-70 at Warrenton

Work Zone Info:  Project inactive until June - Traffic will be reduced to one lane at the work zone.

Project Status:  99% complete - Waiting on completion of exceptions from semi-final inspection

Estimated Completion:  Fall 2008

 

Maintenance

-- Route 47 - Edgerut repair north of Warrenton

Back to Top

 

   
   