When it was first developed, the Long-Range
Transportation Plan applied no fiscal constraints to the process.
When it sought public opinion, MoDOT did not ask citizens to
base their expectations on costs. The department asked for their
opinions on what the states transportation priorities
should be and asked them to rank the priorities. MoDOT used
the results of the public input processes and engineering principles
to determine the system needs. The department also identified
the existing gap between the current investment level and what
it would take to fund all the needs.
The gap is enormous. While the needs are real, MoDOT realizes
the level of funding sufficient to meet all transportation
expectations probably never will be reached. Establishing
goals that move toward meeting these expectations is a more
reasonable approach.
For example, Missourians told MoDOT they would like 12-foot
lanes, wider shoulders and smoother pavement on the collector
routes. Collector routes normally carry local traffic. Most
lettered routes are collectors. The estimated cost to upgrade
all collectors to this condition was $4.1 billion. Although
these roads make up 72 percent of the state highway system,
they carry only 18 percent of the traffic. With the limited
resources available, upgrading these roads is not a high priority.
Most funds will be devoted to the National Highway System
(NHS) and remaining arterial roads. The collectors for the
most part will be maintained at current levels. The National
Highway System includes roadways considered to be of state
and national significance. It consists of all interstate routes
and other major highways. Arterials generally carry traffic
to destinations within the state or serve as connectors to
the NHS. Remaining arterials are those not included in the
NHS.
While all modes of transportation have needs that cannot be
met with existing funding, highways and bridges, passenger
rail and bus service between cities, and public transportation
have the costliest needs. Establishing priorities among each
modes needs allows MoDOT to meet the most important
needs first.
- Highway and bridge investments will concentrate on the
NHS and remaining arterials and establish goals for the
entire highway and bridge system.
- The states most important passenger rail needs
can be met by implementing the Midwest Regional Rail Initiative
on existing rail tracks with modifications between St.
Louis and Kansas City.
- Missourians consistently rated public transportation
as a high-priority need. Trying to meet 90 percent of
the established needs will bring significant improvements
in urban and rural areas.
The changing economy affects the costs in the Long-Range
Transportation Direction and what improvements Missourians
can expect in their transportation system. It is difficult
to predict economic changes for a long period of time. The
Long-Range Transportation Direction, for example, uses a
20-year timeframe. The longer the time between when a projects
cost is established and when that project begins, the more
uncertain the cost projection becomes. The uncertainty is
greatest for projects that are anticipated more than five
years in the future.
When, for example, this documents development started
in 1999, the economy was robust. Since then, economic conditions
have changed, resulting in less money available through
the departments usual funding sources. These types
of changes, along with possible upcoming changes to federal
laws governing transportation funding, may affect transportation
revenue. It is impossible to predict with certainty what
new funding levels and/or restrictions might someday be
applied.
MoDOT assumes costs of projects in all modes of transportation
will grow at approximately 3 percent per year in the first
five years. Beyond five years, the average growth and inflation
factor is assumed to be 4.5 percent annually. These estimates
are based on a combination of historical data and the best
practices of other states. These cost increases have a dramatic
impact on the gap between existing resources and transportation
needs.
This gap right now is more than $1 billion a year for 20
years. This figure is not adjusted for inflation or growing
project costs over time. When those factors are calculated,
the resulting gap almost doubles, climbing to $2 billion
a year.
Chart
1 is an example of how variations in revenues and needs
can affect the funding gap. It shows the gap between highway
and bridge anticipated revenues and estimated needs for
the next 10 years. As MoDOTs revenues decline, it
is clear the gap will continue to widen over time. The declining
revenue reflects several factors. It shows the steep drop-off
in 2004 when MoDOT no longer is using bond money to finance
projects and is repaying the existing bond debt using program
funds. It shows another drop-off in 2008 when the 1992 six-cent
gas tax is eliminated. At the same time, assuming the project
growth and inflation factors discussed above, the needs
continue to increase, resulting in an ever-growing gap. |