Rte. 364 & I-270 Interchange Improvements

This interchange improvement project is part of the Interstate 270 and Dorsett/Page Project. To learn more, visit the I-270 and Dorsett/Page website

 

What’s the Latest on the Northbound Interstate 270 Ramp to Westbound Route 364?

To reduce the impact to commuters during the construction of the western portion of Interstate 64, the construction on the ramp will begin in summer 2010.

What Is The Problem With The Existing Northbound Interstate 270 Ramp To Westbound Route 364?

The existing loop ramp from northbound Interstate 270 to westbound Route 364 is not designed to handle current traffic volumes, which results in daily congestion. In fall 2003, approximately 3,200 vehicles were using this ramp. In fall 2004, more than 11,000 vehicles were using this ramp. There are also conflicts between vehicles merging onto westbound Route 364 and vehicles merging onto the ramp to southbound Interstate 270. This creates a "weaving movement" and contributes to congestion.



What Is The Proposed Solution?

MoDOT will construct a new two-lane circular ramp from northbound Interstate 270 to westbound Route 364.

 

View a map showing the proposed I-270 and Route 364 (Page Avenue) improvements. (3.98 mb, 1 page)

 

A second, new auxiliary lane will also be constructed alongside the existing auxiliary lane on northbound Interstate 270 between Olive Boulevard and Route 364 (Page Avenue).

 

View a map showing the proposed auxiliary lane improvements (5.60 mb, 1 page)

The documents are provided in Acrobat Reader format. Free Acrobat Reader download PDF Icon

Estimated Project Cost:

Estimated construction cost to improve the Interstate 270 and Route 364 interchange: $22 million

 

Current Project Timeline

November 15, 2005
Held open house public hearing.

Through 2006
MoDOT proceeding with right of way acquisition.

Mid 2007

Final design will be complete

May 2009
The project will be bid on by contractors.

June 2009
The project is expected to be awarded to a contractor.

Summer 2010
Construction begins.

Late 2011
Construction is complete.

 

Who Do I Contact For More Information?

  • Contact MoDOT I-270 and Dorsett/Page Project Director Lee Hillner at
    1-888 ASK MODOT (275-6636) or e-mail lee.hillner@modot.mo.gov